Commissioning of a new factory in Algeria ()

BERALMAR has just commissioned a new factory in Algeria, in the city of Adrar. This is the TIMADANINE 2 factory, which, as its name indicates, is this manufacturer's second production line. The first line, with 250 tons/day of block production, was also supplied by Beralmar in 2010. In this case however, the new line just commissioned is of a very different size: 900 tons/day of various formats of ceramic blocks.

BERALMAR’s supply for this new production line consists of:

- Cutting mechanisms.

- Loading of drying racks by robots.

- MESTRAL semi-continuous dryer.

- Unloading from dryer and stacking of cars by robots.

- PRESTHERMIC-E model tunnel kiln.

- Destacking by robots.

- Pallet formation and packaging mechanisms.

Obviously, the fuel used in the kiln will be natural gas which is abundant and cheap in Algeria.

The commissioning was a complete success and the first car came out without any broken parts and with the expected quality.

The factory is in the middle of the Sahara desert, 1400 kilometers from the coast and the climate is of course extreme, temperatures normally rising to 50ºC in the summer.

This is the 6th factory supplied by BERALMAR in Algeria and, as we said, the second one for this customer, whom we thank once again for the confidence it has shown in BERALMAR.